168 trackers with bifacial modules for an off-grid, self-consumption hybrid diesel - PV industrial site (805kWp).
ENERWHERE
Abu Dhabi - United Arabian Emirates
May 2019
42 trackers with mono and bifacial modules for industrial self-consumption site (180kWp).
ENERWHERE
Abu Dhabi - United Arabian Emirates
October 2018
12 trackers HLPV-12 (52kWp) self-consumption project for ADWEA (Abu Dhabi Water & Electric Auth.).
EUROPEAN ENERGY
DTU, Roskilde - Denmark
August 2018
2 trackers with mono and bifacial modules as part of a technical comparison of modules and structures (HeliosLite 1.5 axis, 1 axis Hz, fixed tilt rack).
RUBICON
Cape Town - South Africa
October 2017
Show case tracker demonstrator for South African market.
SUMITOMO
Miyazaki - Japan
September 2017
Installation with Sumitomo engineers of a HeliosLite tracker with Sumitomo HCPV modules.
TENERGIE
Rians - France
September 2017
Commissioning of a 80 dual axis tracker PV plant (627kWp) using HeliosLite’s electronic control system.
COTE D'OR
Côte d'Or - France
July 2017
3 tracker pilot project (9kWp) for self-consumption.
IRESEN
Ben Guérir - Morocco
November 2016
COP22 demonstrator in collaboration with Photowatt for IRESEN (Institut de Recherche pour des Energies Solaires et Energie Nouvelle).
ARAYMOND
Grenoble - France
October 2016
6 tracker pilot project (15kWp) for self-consumption at ARaymond Grenoble. Over 30MWh of energy produced to date.
HELIOSLITE
Le Bourget du Lac - France
June 2016
Proof of Concept passed 34% power increased measured for one day. Upgraded model now installed.
UNIVERSITE D'AJACCIO
Ajaccio - France
September 2015
HeliosLite HL35 tracker CPV (10.4kWc) installed at Université de Corse with Cofely INEO.
EDF
Fontainebleau - France
June 2015
HeliosLite HL25 installation at EDF R&D « Les Renardières » site. Public tender reply.
PHOTOWATT
M'Bour - Senegal
March 2015
8 kWc demonstrator of 2x HeliosLite HL25 tracker equipped with Photowatt PV modules.
CLUB MED
Cap Skiring Village - Senegal
December 2014
8 kWc demonstrator of 2x HeliosLite HL25 tracker equipped with Photowatt PV modules.
CEA-INES
Le Bourget du Lac - France
October 2014
HL35 tracker with 4 Soitec CX M500 (9.3kWc). Performance data measured by the CEA-INES.
HL20 HeliosLite tracker CPV Proof of Concept passed in Oct 2013 with performance data measured by the CEA-INES. Grid connected since March 2014 with more than 6MWh produced (in spite of the poor CPV climate).